NSE circular NCL/EGR/76143 · 03 Sept 2026
Official title
Connect2NSE (C2N) connectivity from Disaster Recovery Site
Official record
Open source pageSummary
Check the official recordNSE Clearing Limited conducts Electronic Gold Receipt segment operations from its Disaster Recovery site on September 03, 2026, and September 04, 2026. Members do not change configuration settings or connection parameters for N-MASS, NCMS, or NCIS applications. These applications remain unavailable for live operations or updates from 01:00 hours to 08:00 hours on September 05, 2026.
What you must do
Key dates
| Department: ELECTRONIC GOLD RECEIPT | |---|---| | Download Ref No: NCL/EGR/76143 | Date: September 03, 2026 | | Circular Ref. No: 317/2026 | |
All Custodians/ Members,
Sub: - Connect2NSE (C2N) connectivity from Disaster Recovery Site
Members are requested to note that NSE Clearing Ltd will be conducting its operations for the Electronic Gold Receipt Segment from its Disaster Recovery (DR) Site on September 03, 2026 and September 04, 2026.
In this regard, please note the following:
Members accessing N-MASS, NCMS and NCIS applications through different modes of connectivity (e.g., internet or leased line) are not required to make any changes in configuration settings/ connection parameters to connect to C2N applications from Disaster Recovery Site.
Members are requested to note that N-MASS , NCMS and NCIS applications shall not be available for any live operations or updates between:
01:00 hrs. on September 05, 2026, to 08:00 hrs. on September 05, 2026.
Members/Custodians are advised to take note of the above.
For and on behalf of
NSE Clearing Limited
Ashwini Goraksha
Associate Vice President
| Telephone No | Email id |
|---|---|
| 1800 2660 050(IVR Option – 2) | cm_clearing_ops@nsccl.co.in |